Active Upstream Oil & Gas Location

Client

  • Oil & Gas Producer

 

Problems

  • Hydrocarbons
  • C6 - C10 ± 1260 ppm
    (Criteria = 260 ppm)
  • C10 - C16 ± 1700 ppm
    (Criteria = 900 ppm)
  • Ethyl-Benzene ± 6.46 ppm
    (Criteria = 0.19 ppm)

 

Project Summary

The impacted soil was contaminated with petroleum hydrocarbons. The targeted remediation goals were the Alberta Tier 1 hydrocarbon guidelines for fine-grained surface soil using a natural area land-use. On-site, there was a total of approximately 5,842 m3 to be treated. The scope of work was to process material by means of our dual-drive Allu bucket attachment.

 

Results and Advantages

  • Achieved successful remediation of Ethyl-Benzene, F1 (C6 - C10) and F2 (C10 - C16) petroleum hydrocarbons (results were <0.10 ppm, 87 ppm and 332 ppm respectively).

 

Duration and Cost

  • Project completed in 2 months (4 months ahead of schedule).
  • Project Cost:
    ± $124,000.00 (on budget)

 

Download PDF